For purposes of any determination under paragraph (1) and any review of the determination in any court, the purposes of this section supplement otherwise applicable State law.
For purposes of this section, the standard referred to in subsection (a) shall provide that an owner or operator of a waste energy recovery project identified on the Registry that generates net excess power shall be eligible to benefit from at least 1 of the options described in subsection (c) for disposal of the net excess power in accordance with the rate conditions and limitations described in subsection (d).
The electric utility shall purchase the net excess power from the owner or operator of the eligible waste energy recovery project during the operation of the project under a contract entered into for that purpose.
The electric utility shall transmit the net excess power on behalf of the project owner or operator to up to 3 separate locations on the system of the utility for direct sale by the owner or operator to third parties at those locations.
The term “per unit transmission costs” means the total cost of those transmission services purchased or provided by a utility on a per-kilowatt-hour basis as included in the retail rate of the utility.
The options described in paragraphs (1) and (2) in subsection (c) shall be offered under purchase and transport rate conditions that reflect the rate components defined under paragraph (1) as applicable under the circumstances described in paragraph (3).
Sales made by a project owner or operator of a facility under the option described in subsection (c)(1) shall be paid for on a per kilowatt hour basis that shall equal the full undiscounted retail rate paid to the utility for power purchased by the facility minus per unit distribution costs, that applies to the type of utility purchasing the power.
If the net excess power is made available for purchase at voltages that must be transformed to or from voltages exceeding 25 kilovolts to be available for resale by the utility, the purchase price shall further be reduced by per unit transmission costs.
Transportation by utilities of power on behalf of the owner or operator of a project under the option described in subsection (c)(2) shall incur a transportation rate that shall equal the per unit distribution costs and per unit distribution margin, that applies to the type of utility transporting the power.
If the net excess power is made available for transportation at voltages that must be transformed to or from voltages exceeding 25 kilovolts to be transported to the designated third-party purchasers, the transport rate shall further be increased by per unit transmission costs.
In a State with a competitive retail market for electricity, the applicable transportation rate for similar transportation shall be applied in lieu of any rate calculated under this paragraph.
No utility shall be required to purchase or transport a quantity of net excess power under this section that exceeds the available capacity of the wires, meter, or other equipment of the electric utility serving the site unless the owner or operator of the project agrees to pay necessary and reasonable upgrade costs.
Except as otherwise provided in paragraphs (1) and (2), the procedures for the consideration and determination referred to in subsection (a) shall be the procedures established by the State regulatory authority or the nonregulated electric utility.
If a State regulatory authority (with respect to each electric utility for which the authority has ratemaking authority) or nonregulated electric utility declines to implement any standard established by this section, the authority or nonregulated electric utility shall state in writing the reasons for declining to implement the standard.
The Administrator shall include in an annual report submitted to Congress a description of the lost opportunities for waste-heat recovery from the project described in subparagraph (A), specifically identifying the utility and stating the quantity of lost energy and emissions savings calculated.
If a State regulatory authority (with respect to each electric utility for which the authority has ratemaking authority) or nonregulated electric utility declines to implement the standard established by this section, the project sponsor may submit a new petition under this section with respect to the project at any time after the date that is 2 years after the date on which the State regulatory authority or nonregulated utility declined to implement the standard.